Construction phase 3
The U55 from Hauptbahnhof to the Brandenburg Gate
The initial pit for the tunnelling work corresponds roughly to
the future entry structure (approx. 28 x 25 m) of the metro
station. Due to the high groundwater level, as well as the
prohibition on lowering it, the pit is sealed on all sides and
secured in the soil with anchors.
The shaft can be finished in approximately 10 weeks. A cover over
the future structure will first be built on the subterraneous
curtains. Excavation will then be performed under this cover.
The main advantage of this method is that it minimizes
inconvenience for local residents by enabling most of the
construction work to take place under the cover.
Construction phase 3
Action:
Temporary cover, soil excavation
Emissions:
Building the cover: moderate noise pollution. Construction work
will then be done underground.
Excavation:
Low noise pollution during excavation. Moderate noise pollution
from loading and traffic. Dust pollution is reduced by
sprinkling.
Material transport:
Removal of excavated earth, delivery of concrete.
Site traffic:
2-3 lorries per hour